The Jack Creek and Indian Creek culvert replacement projects are nearing completion. The Jack Creek culvert is installed and the creek is now running through the culvert. The road portion (paving and guardrail) will not be complete until the end of the month.
The newly shaped streambed inside the Jack Creek culvertThe Indian Creek culvert has been assembled and is being
backfilled this week. The
streambed gravel is being placed inside the culvert. That work should be complete by the September 22.
Backfilling the Indian Creek culvert this week.The Coleman Creek Irrigation Modification Project bids were
received last week. A construction contract will be executed next week with the lowest responsive and responsible bidder. That project is expected to begin in mid October. It involves removal of the existing dam and installation of rock weirs and a fish screen. The new diversion configuration will include automated gates and telemetry for the water measuring devices.
The
Manastash Restoration Project make a significant leap this fall. The Barnes Road Fish Screen project will begin construction on October 5
th. That project is contracted by the District and includes a fish ladder, a fish screen and water measuring equipment with telemetry and automated gates. The
MWDA/Consolidated diversion fish screen structure will also be constructed this fall. That project is contracted directly by
BPA through
HDR and includes a fish screen, rock weirs for fish passage, and water measuring equipment with telemetry and automated gates.
AL