Friday, October 23, 2009

Fall Projects

Construction of the Jack and Indian Creek culverts is 99% complete. Remaining work mostly involves the road (striping, etc.). We are now working to replant the riparian areas at each project site.


WCC Planting Crew at Indian Creek


Another component of the Manastash Creek Restoration Project is set to begin next week. A sprinkler conversion project for a landowner in the Menastash Water Ditch Association (MWDA) will result in saved water placed in the Trust Water Rights Program in perpetuity. The trust water associated with this project brings the total water secured for Manastash Creek to 4.7 cubic feet per second (cfs). The intial goal is to reach 6 cfs.

Dan Swan (PSE), Sherry (KCCD), and Bob Gregerich (MWDA) discuss the eletrical service needs for the sprinkler conversion project.