The Cherry Creek project is moving forward. The contractor has diverted the creek around the upstream work area and begun constructing the first four rock weirs. In the process of dewatering the work site, a fish rescue was conducted by WDFW. See the photos below.
 |
| The contractor constructed a bulk bag dam to divert the creek into the bypass channel. |
 |
| The bypass channel is lined and several hundred feet long. |
 |
| The fish rescue crew working in the cold and snow. |
 |
| A few of the 85 rainbow trout removed during the first session. They ranged in size from 70 mm to 370 mm (2.75 to 14.5 inches). |
 |
| Beginning to construct the first of the four rock weirs. |