Progress continues at Keach-Jensen. Last week the Sutton Bank Protection project was completed. It involved rocks and root-wads to stabilize a section of bank upstream of Keach-Jensen. At the diversion structure, there was a small pour last week, and then a lot of preparation for a big pour today. The big pour was for the slab that stretches the length of the structure. The next pour will be the outside wall (on the creekside). It is scheduled for this Friday. Once that wall is in place, the rock weirs can be completed and the site is ready for the creek to be at least partially returned to it's channel.
 |