Monday, November 29, 2010

Manastash Construction Update

Keach-Jensen is moving right along!  The outside wall is complete, as are the rock weirs and the fish bypass pipe. The work continues on the outlet portions of the structures.

Forming the slab for the Keach Ditch outlet

Forming the slab for the Jensen Ditch outlet
 
Pouring the slab for the Jensen Ditch outlet

Finishing the rock weirs after the outside wall was completed.

The MWDA/Consolidated Diversion had a few punch list items left, including a security fence.  The fence is now installed. Other remaining items include a debris boom in front of the headgates and work on the programing the automation.

The security fence was completed at the MWDA/Consolidated Diversion.